黄文斌, 吴俊杰, 米占宽, 魏匡民, 王芳. JL混凝土面板堆石坝面板破损机理反演分析研究[J]. 岩土工程学报. DOI: 10.11779/CJGE20250110
    引用本文: 黄文斌, 吴俊杰, 米占宽, 魏匡民, 王芳. JL混凝土面板堆石坝面板破损机理反演分析研究[J]. 岩土工程学报. DOI: 10.11779/CJGE20250110
    Back analysis and research on the damage mechanism of JL concrete-faced rockfill dam[J]. Chinese Journal of Geotechnical Engineering. DOI: 10.11779/CJGE20250110
    Citation: Back analysis and research on the damage mechanism of JL concrete-faced rockfill dam[J]. Chinese Journal of Geotechnical Engineering. DOI: 10.11779/CJGE20250110

    JL混凝土面板堆石坝面板破损机理反演分析研究

    Back analysis and research on the damage mechanism of JL concrete-faced rockfill dam

    • 摘要: JL面板堆石坝最大坝高140.3m,采用花岗岩和石英斑岩填筑,运行初期大坝出现了止水破坏、面板裂缝、严重渗漏等问题,影响了大坝的正常运行。本文基于大坝沉降数据和面板现场检测资料反演研究了JL大坝运行初期面板破损机理,采用三维精细化数值模拟方法,再现了堆石坝体变形过程和混凝土面板应力演化性状。研究认为,大坝初次蓄水时发生的水位骤降导致了面板止水破坏,渗水冲蚀垫层区引起了面板脱空,造成面板受水压力逐步破损和出现贯穿性裂缝。通过降低水位,对水上破损面板覆盖修复,水下破损面板浇筑环氧混凝土和脱空区灌浆,大坝渗漏量得到控制。JL大坝面板破损案例给面板堆石坝设计施工以深刻的启示:面板堆石坝设计施工应保证各坝料之间的变形协调确保面板与垫层密实接触;运行期应尽量避免水位骤降以防止止水破坏和垫层料流失,影响面板受力;垫层、过渡、堆石区之间的反滤关系要严格满足,避免面板开裂后垫层料细颗粒向坝内的流失,导致面板受力状态恶化。

       

      Abstract: The JL Concrete Faced-Rockfill Dam (CFRD) has a maximum height of 140.3 m and is constructed using granite and quartz porphyry rockfills. During its initial operation, the dam encountered issues such as water-stop damage, slab cracking, and excessive seepage, which affected its normal operation. This study analyzed the damage mechanism of the slab during the early operation based on settlement data and slab inspection records. By Using a 3D refined numerical simulation method, the deformation process of the rockfill dam and the stress evolution of the concrete slab were reproduced. Research indicated that the sudden drop of water level that occurred during the initial impoundment led to the damage of the slab water-stops, seepage erosion of the cushion led to gaps between the slab and the rockfill, which further deteriorated the stress of the slab, resulting in progressive damage and cracks. After lowering the water level, the damaged slab was repaired and the gaps were treated with grouting. The leakage of the dam has been controlled. The case of the JL CFRD gives profound enlightenment to the design and construction of CFRDs: The design and construction of the CFRD should ensure that the deformation between the material zones is coordinated so that the slab is in intimate contact with the cushion; During operation period, sudden drop of water level should be avoided as much as possible to prevent waterstops damage and loss of cushion material. The filter criterion of the cushion zone, transition zone, and rockfill zone should be strictly satisfied to avoid the loss of fine particles of cushion material once the slab cracked, which will lead to further damage of the slab.

       

    /

    返回文章
    返回