Citation: | PAN Wei-qiang. Monitoring and analysis of ground settlement during pipe roof construction of pipe-jacking groups in soft soil areas[J]. Chinese Journal of Geotechnical Engineering, 2019, 41(S1): 201-204. DOI: 10.11779/CJGE2019S1051 |
[1] |
关永平. 地铁暗挖车站STS管幕支护结构的力学性能研究[D]. 沈阳: 东北大学, 2015.
(GUAN Yong-ping.Research on mechanical property of the STS structure used to construct shallow buried subway station[D]. Shenyang: Northeastern University, 2015. (in Chinese)) |
[2] |
刘应亮. 大直径曲线管幕顶进过程中地层变形控制及监测[J]. 现代隧道技术, 2017, 54(6): 210-216.
(LIU Ying-liang.Control and monitoring of ground deformation during jacking of a large-diameter curved tabular roof[J]. Journal of Northeastern University, 2017, 54(6): 210-216. (in Chinese)) |
[3] |
李慎刚, 韩健勇, 石建军, 等. STS新管幕工法钢管顶进现场试验[J]. 东北大学学报, 2016, 37(10): 1469-1473.
(LI Shen-gang, HAN Jian-yong, SHI Jian-jun, et al.Field test on steel pipe jacking by STS method[J]. Rock and Soil Mechanics, 2016, 37(10): 1469-1473. (in Chinese)) |
[4] |
陈韶章, 苏宗贤. 韩国最大暗挖地铁车站施工技术[J]. 施工技术, 2012, 41(2): 46-49, 101.(CHEN Shao-zhang, SU Zong-xian. The largest tunnel station in Korea the express bus terminal subway station, Lot 913, Seoul Subway Line 9[J]. Construction Technology, 2012, 41(2): 46-49, 101. (in Chinese))
|
[5] |
黎永索, 张可能, 黄常波, 等. 管幕预筑隧道地表沉降分析[J]. 岩土力学, 2011, 32(12): 3701-3707.
(LI Yong-suo, ZHANG Ke-neng, HUANG Chang-bo, et al.Analysis of surface subsidence of tunnel built by pipe-roof pre-construction method[J]. Rock and Soil Mechanics, 2011, 32(12): 3701-3707. (in Chinese)) |
[1] | AN Peng, ZHANG Jie, NI Wankui, MA Xinchao, HU Xingqun, ZHANG Changbo. Settlement and deformation characteristics of high fill of Luojiahe expansive soil in Ankang Airport[J]. Chinese Journal of Geotechnical Engineering, 2023, 45(4): 833-839. DOI: 10.11779/CJGE20220071 |
[2] | LI Bin, GAO Chao, ZHANG Jia-ying. Instantaneous settlement of immersed tube tunnel of Hong Kong-Zhuhai-Macao Bridge[J]. Chinese Journal of Geotechnical Engineering, 2021, 43(S2): 263-266. DOI: 10.11779/CJGE2021S2062 |
[3] | XIE Xiong-yao, YI Cheng-min, LI Wei-ping, FANG Yong-gang. Safety analysis of settlement monitoring data of joints of Yongjiang immersed tube tunnel during operation period[J]. Chinese Journal of Geotechnical Engineering, 2019, 41(12): 2338-2344. DOI: 10.11779/CJGE201912020 |
[4] | HUANG Qi-huan, WANG Qing-qing, HE Ning, WANG Yi-an, ZHOU Yan-zhang. Monitoring time-series settlements of breakwaters based on PSI[J]. Chinese Journal of Geotechnical Engineering, 2019, 41(4): 761-768. DOI: 10.11779/CJGE201904021 |
[5] | WANG Wei, XU Kai, WANG Hai-long, LI Lu-lu. Application of real-time monitoring technology to foundation settlement of sloping breakwaters in construction[J]. Chinese Journal of Geotechnical Engineering, 2017, 39(s1): 85-90. DOI: 10.11779/CJGE2017S1017 |
[6] | Zhu Cai-hui, LI Ning, LIU Ming-zhen, WEI Yi-feng. Spatiotemporal laws of post-construction settlement of loess-filled foundation of Lüliang Airport[J]. Chinese Journal of Geotechnical Engineering, 2013, 35(2): 293-301. |
[7] | Settlement of overlaying soil caused by decompression of confined water[J]. Chinese Journal of Geotechnical Engineering, 2011, 33(1). |
[8] | YANG Youhai, WANG Jianjun, WU Jinguang, LI Changshan. Informationized construction monitoring analysis of deep foundation pit for Qiutao Road station of Hangzhou Metro[J]. Chinese Journal of Geotechnical Engineering, 2008, 30(10): 1550-1554. |
[9] | HU Qunfang, HUANG Hongwei. Analysis and monitoring on shield tunneling under existing adjacent tunnel[J]. Chinese Journal of Geotechnical Engineering, 2006, 28(1): 42-47. |
[10] | KE Han, CHEN Yunmin. Calculation of post-closure settlement of landfills[J]. Chinese Journal of Geotechnical Engineering, 2003, 25(6): 742-746. |