• 全国中文核心期刊
  • 中国科技核心期刊
  • 美国工程索引(EI)收录期刊
  • Scopus数据库收录期刊
刘孟波, 廖少明, 陈立生, 赵国强, 徐伟忠. 盾构在泡沫混凝土中的接收及现场实测分析[J]. 岩土工程学报, 2020, 42(11): 2006-2014. DOI: 10.11779/CJGE202011005
引用本文: 刘孟波, 廖少明, 陈立生, 赵国强, 徐伟忠. 盾构在泡沫混凝土中的接收及现场实测分析[J]. 岩土工程学报, 2020, 42(11): 2006-2014. DOI: 10.11779/CJGE202011005
LIU Meng-bo, LIAO Shao-ming, CHEN Li-sheng, ZHAO Guo-qiang, XU Wei-zhong. In-situ measurements of shield machine receiving in foamed concrete[J]. Chinese Journal of Geotechnical Engineering, 2020, 42(11): 2006-2014. DOI: 10.11779/CJGE202011005
Citation: LIU Meng-bo, LIAO Shao-ming, CHEN Li-sheng, ZHAO Guo-qiang, XU Wei-zhong. In-situ measurements of shield machine receiving in foamed concrete[J]. Chinese Journal of Geotechnical Engineering, 2020, 42(11): 2006-2014. DOI: 10.11779/CJGE202011005

盾构在泡沫混凝土中的接收及现场实测分析

In-situ measurements of shield machine receiving in foamed concrete

  • 摘要: 泡沫混凝土盾构接收工法是利用泡沫混凝土为盾构接收掘进提供平衡条件,同时起到稳定洞口土体和防止突涌水等作用,其中盾构掘进参数的合理选取是该工法的关键点。以上海地铁14号线云山路站泡沫混凝土盾构接收为背景,通过现场测试,研究了盾构在泡沫混凝土中的关键掘进参数、端墙和侧墙的压力变化、泡沫混凝土深层位移变化规律及其相关性。分析发现:①盾构从加固体进入泡沫混凝土至最终顶进到位,推力、扭矩和土仓压力的量值和波动呈现先下降再上升的规律;②盾构推进在泡沫混凝土端墙产生的压力增量明显大于侧墙,侧墙压力增量为20~30 kPa,端墙压力最大增量达120 kPa,为初始值的6~7倍;③端墙上压力变化与盾构掘进状态呈现高度相关性,随盾构开停推进循环,墙上压力呈“锯齿状”累积上升;④随着切口接近端墙,单位推进距离产生的端墙压力增量变大,且盾壳全部进入泡沫混凝土箱体时,端墙压力发生突增;⑤盾构前方泡沫混凝土的侧向位移沿盾构推进方向最大约10 mm,呈现中间大、拱顶和拱底小的“凸分布”;端墙附加压力呈“梯形”分布,拱顶压力增量极小,中部增大约60 kPa,底部增大约120 kPa。实测分析成果可为泡沫混凝盾构接收工法的井壁设计、材料优化以及盾构参数的控制提供重要技术参考,工程的成功实施也为该工法的进一步推广应用打下了基础。

     

    Abstract: The foamed concrete can be used in the shield machine receiving to stabilize the ground near the soft eye and to prevent water inrush. One of the critical points of this method is to control the shield tunneling parameters. Based on the shield machine receiving in the foamed concrete at Yunshan Road Station of Shanghai metro line No. 14, the critical parameters, change of pressures on end and side walls, deep displacements of the foamed concrete and their correlation during the tunneling process in the foamed concrete are studied through in-situ measurements. According to the analysis, the main findings are as follows: (1) The magnitude and fluctuation of thrust, torque and pressure in the earth cabin all experience a "down then up" process. (2) When the shield advances in the foamed concrete, the pressure increment on the end wall is more significant than that on the side wall. The change of pressure on the side wall is 20~30 kPa, while the maximum pressure increment on the end wall is up to 120 kPa, which is 6~7 times the initial value. (3) The pressure on the end wall accumulates in a "zigzag" pattern with the starting and stopping of the advance cycle of shield construction. (4) As the cutter head is closer to the end wall, the pressure increment generated by the unit advance distance increases accordingly. (5) The foamed concrete in front of the shield presents a "convex distribution" along the advancing direction. The pressure increment on the vault of the end wall is the minimum, with an increase of about 60 kPa in the middle and about 120 kPa in the bottom. These results can provide an essential reference for shaft design, material optimization and parameter control. The successful implementation of this project also lays a foundation for the further popularization and application of the proposed method.

     

/

返回文章
返回